QIC Cleveland Offices

Complete build out of 18,600-sf on the 15th floor in Fifth Third Center in downtown Cleveland. High end finishes at reception area, conference, board rooms. General open office for remainder of space with pods of offices and quiet rooms around the perimeter. Scope includes LED acoustical propellers and an open ceiling -- very unusual for a high rise building. Also includes Infinium glass office fronts.

Completed this project in 12-weeks, including full floor demolition.   After construction began the client added $300,000 in new audio visual equipment which required new core drills.  By re-sequencing in close collaboration with our subcontractors, we completed this work without extending the schedule.  Our progress allowed the Owner's FF&E vendors to access the project one week ahead of scheduleReturned $14,000 in unspent allowances.  Achieved 54.3% diverse subcontracting participation.